If you need to know about batteries; you’ve come to the right place 点击这里访问我们的中文网站

Belectric

Belectric storage system approved for frequency response

Tue, 05/26/2015 - 16:38 -- Anonymous
News image: 
Belectric storage system approved for frequency response.
Share page with AddThis

Solar power company Belectric’s lead-acid battery storage system has been prequalified to provide 1.3MW of frequency control for Germany’s high voltage grid.

The €560,000 ($609,000) 948kWh Energy Buffer Unit (EBU) was initially installed to provide backup at the 67.8 MW Alt Daber solar project in Brandenburg, Germany.

The system will now provide frequency response to the German transmission network operator (TNO) 50Hertz, and will assist in frequency across the country’s high voltage grid from the Alt Daber plant.

The EBU includes power inverter and a medium voltage transformer. Depending on configuration, it has the ability to deliver between 800 and 1400kW of power storage.

It can also be prequalified for frequency response on the German transmission network at up to 650 kW, taking account of the reserve capacity required by German TNOs.

Subscribe to Belectric